PROJECT HIGHLIGHTS

  • Replaced existing units with packaged cooling rooftop units and single duct shut off variable air volume (VAV) terminals with hot water reheat coils and new DDC control 

  • Existing ductwork was re-used where possible 

  • Existing pumps were replaced with high efficiency boilers and variable speed pumps

  • Modified the fire alarm system, electrical services, and building structure to accommodate the system